logo

Modern Water Treatment for Historic Institute

Client

Commonwealth of Pennsylvania Department of General Services

Completion Date

October 14th, 2020

Role

General Contractor

The project consists of the construction of a new membrane filtration plant and a new membrane filtration building. Housed in the building will be 3 membrane filtration units, plate settlers, water treatment chemicals and a chlorine gas room. Renovations to existing facilities include the addition of new pumping facilities and modification of the existing intake on Sandy Creek. Also included are the addition of new and modifications to existing underground piping and the construction of a new submersible wastewater pump station.

$3,815,059.00

thick line Created with Sketch.
Contract Value

Polk, PA (Venango County)

thick line Created with Sketch.
Location
Share by: